Gantt: work breakdown
A parentField turns flat rows into phases and the tasks under them. This page
covers the summary bar a phase draws, how its percent is worked out, collapse,
and what a folded phase still does for the links and the planning passes.
<script lang="ts">
import { SvGrid, type GridColumns, type GanttDependency } from '@svgrid/grid'
import { enableGanttView } from '@svgrid/enterprise'
enableGanttView()
type Task = {
id: string
name: string
owner?: string
start: string
end?: string
progress?: number
parentId?: string | null
milestone?: boolean
}
const pad = (n: number) => String(n).padStart(2, '0')
const isoDay = (d: Date) => `${d.getFullYear()}-${pad(d.getMonth() + 1)}-${pad(d.getDate())}`
const base = new Date()
base.setHours(0, 0, 0, 0)
base.setDate(base.getDate() - ((base.getDay() + 6) % 7))
const at = (dayOffset: number) => {
const d = new Date(base)
d.setDate(d.getDate() + dayOffset)
return isoDay(d)
}
let data = $state<Task[]>([
{ id: 'p1', name: 'Discovery', parentId: null, start: at(0), owner: 'Priya' },
{ id: 't1', name: 'Interviews', parentId: 'p1', start: at(0), end: at(4), progress: 100, owner: 'Priya' },
{ id: 't2', name: 'Synthesis', parentId: 'p1', start: at(5), end: at(11), progress: 40, owner: 'Marco' },
{ id: 'p2', name: 'Build', parentId: null, start: at(12), owner: 'Sven' },
{ id: 'p2a', name: 'Back end', parentId: 'p2', start: at(12), owner: 'Sven' },
{ id: 't3', name: 'Data model', parentId: 'p2a', start: at(12), end: at(18), progress: 30, owner: 'Sven' },
{ id: 't4', name: 'API', parentId: 'p2a', start: at(19), end: at(25), progress: 0, owner: 'Sven' },
{ id: 't5', name: 'Front end', parentId: 'p2', start: at(15), end: at(29), progress: 0, owner: 'Mia' },
{ id: 'm1', name: 'Launch', parentId: null, start: at(30), milestone: true },
])
const dependencies: GanttDependency[] = [
{ id: 'd1', from: 't1', to: 't2' },
{ id: 'd2', from: 't2', to: 't3' },
{ id: 'd3', from: 't3', to: 't4' },
{ id: 'd4', from: 't5', to: 'm1' },
]
const columns: GridColumns<Task> = [
{ field: 'name', header: 'Task', width: 200 },
{ field: 'owner', header: 'Owner', width: 100 },
]
</script>
Phases from a parent field
Set parentField to the field holding each row's parent id and the flat
rows nest into a tree, to any depth. A row with children gets a collapse
chevron and draws a summary bar rolled up from every descendant, so a phase
carries no dates of its own - there is nothing to keep in sync by hand.
<SvGrid {data} {columns} getRowId={(r) => r.id}
gantt={{
startField: 'start', endField: 'end',
parentField: 'parentId',
progressField: 'progress',
}} />
Rows whose parent id matches no task become roots rather than vanishing, which is what keeps a filtered-out phase from hiding its tasks. A cycle in the parent links (a under b under a) is broken at the first repeat and the rows involved become roots, so bad data cannot hang the render.
Do not also set
treeData. The Gantt owns its own tree because it needs every descendant - a collapsed phase still contributes to its summary bar - whereastreeDatahides collapsed children from the view before the renderer sees them. Setting both makes summaries under-report, and the grid warns about it in development.
How a summary rolls up
The summary bar spans the earliest start to the latest finish of every descendant, collapsed ones included.
Its percent is weighted by duration, not by task count: a two-day task at 100% beside a six-day task at 0% reads as 25% done, not 50%. Weighting by count would report progress the plan has not made. Descendants with no duration (milestones) weigh nothing, so a parent holding only milestones falls back to their plain mean.
The __duration column on a phase counts the working days of the rolled-up
span, and __slack reports the least slack of any task under it - a phase can
slip only as far as its tightest task, so the room after its own rollup would
be the wrong number.
summaryBars: false draws parents as ordinary bars instead of the thin spine,
for a plan where the phase rows carry real dates of their own.
Collapse
Collapse is the Gantt's own state by default: click a chevron, or the
Collapse all / Expand all button in the toolbar. Hoist it with
collapsed and onCollapseChange to persist it, drive it from elsewhere, or
open a big plan folded:
<script lang="ts">
let collapsed = $state<string[]>(['p2'])
</script>
<SvGrid {data} {columns} getRowId={(r) => r.id}
gantt={{
startField: 'start', endField: 'end', parentField: 'parentId',
dependencies,
collapsed,
onCollapseChange: (next) => (collapsed = next),
}} />
Fold a phase and three things hold:
- The summary keeps the full span. The rollup reads every task, visible or not.
- Links into the phase re-anchor on its summary bar. An arrow from a task outside the phase to a task inside it draws to the bar that now stands for it, rather than disappearing. A link between two tasks of the same folded phase draws nothing - both ends would land on the same bar.
- The planning passes still see the tasks. The critical path and the slack column are computed over the whole plan, so folding does not change which chain is critical; a folded phase over a critical task carries the ring on its summary bar. See the planning layer.
The programme demo opens every one of its forty sites folded, which is how a year of 640 tasks reads as forty bars:
Moving a phase
With editing on, dragging a summary bar moves its whole
subtree by the same offset, and the one onTaskMove call carries the batch
in subtree. Resizing a summary bar is not offered: its length is its tasks'
length.
See also
- Getting started - the basics this page builds on.
- Dependencies - what a link into a folded phase does.