Gantt: dependencies

Links between tasks: the four types, lag and lead, where the links come from, what a violated or cyclic link looks like, and the cascade that keeps every link legal when a task moves.

<script lang="ts">
  import { SvGrid, type GridColumns, type GanttDependency } from '@svgrid/grid'
  import { enableGanttView } from '@svgrid/enterprise'

  enableGanttView()

  type Task = {
    id: string
    name: string
    owner?: string
    start: string
    end?: string
    progress?: number
    parentId?: string | null
    milestone?: boolean
    next?: string[]
  }

  const pad = (n: number) => String(n).padStart(2, '0')
  const isoDay = (d: Date) => `${d.getFullYear()}-${pad(d.getMonth() + 1)}-${pad(d.getDate())}`
  const base = new Date()
  base.setHours(0, 0, 0, 0)
  base.setDate(base.getDate() - ((base.getDay() + 6) % 7))
  const at = (dayOffset: number) => {
    const d = new Date(base)
    d.setDate(d.getDate() + dayOffset)
    return isoDay(d)
  }

  let data = $state<Task[]>([
    { id: 'p1', name: 'Discovery', parentId: null, start: at(0), owner: 'Priya' },
    { id: 't1', name: 'Interviews', parentId: 'p1', start: at(0), end: at(4), progress: 100, owner: 'Priya', next: ['t2'] },
    { id: 't2', name: 'Synthesis', parentId: 'p1', start: at(5), end: at(11), progress: 40, owner: 'Marco', next: ['t3'] },
    { id: 'p2', name: 'Build', parentId: null, start: at(12), owner: 'Sven' },
    { id: 't3', name: 'Implementation', parentId: 'p2', start: at(12), end: at(25), progress: 10, owner: 'Sven', next: ['m1'] },
    { id: 't4', name: 'Documentation', parentId: 'p2', start: at(14), end: at(20), progress: 0, owner: 'Lena' },
    { id: 'm1', name: 'Launch', parentId: null, start: at(26), milestone: true },
  ])

  const dependencies: GanttDependency[] = [
    { id: 'd1', from: 't1', to: 't2' },
    { id: 'd2', from: 't2', to: 't3' },
    { id: 'd3', from: 't3', to: 'm1' },
  ]

  const columns: GridColumns<Task> = [
    { field: 'name', header: 'Task', width: 200 },
    { field: 'owner', header: 'Owner', width: 100 },
  ]

  function writeSpan(row: Task, start: Date, end: Date) {
    row.start = isoDay(start)
    const last = new Date(end.getTime() - 86_400_000)
    row.end = isoDay(last < start ? start : last)
  }
</script>

Link tasks with predecessor -> successor dependencies and the chart draws an arrow between them. from / to are row ids (your getRowId).

<SvGrid {data} {columns} getRowId={(r) => r.id}
  gantt={{
    startField: 'start', endField: 'end', parentField: 'parentId',
    dependencies,
  }} />

Four link types are supported, named for the two edges they join:

type Means The arrow runs
FS (default) Finish-to-start: the successor starts once the predecessor finishes. predecessor's finish -> successor's start
SS Start-to-start: both start together (or the successor later). start -> start
FF Finish-to-finish: both finish together (or the successor later). finish -> finish
SF Start-to-finish: the successor cannot finish before the predecessor starts. start -> finish

An optional lag is in days, negative for a lead:

const dependencies: GanttDependency[] = [
  { id: 'd1', from: 'pour', to: 'cure', type: 'FS' },
  { id: 'd2', from: 'cure', to: 'frame', type: 'FS', lag: 2 },   // two days after curing
  { id: 'd3', from: 'frame', to: 'wire', type: 'SS', lag: 1 },   // wiring starts a day after framing does
  { id: 'd4', from: 'wire', to: 'inspect', type: 'FF', lag: -1 } // inspection wraps a day early
]

How an arrow is routed

An arrow leaves the predecessor on the side its type names and arrives at the successor on the other: a finish-anchored link (FS, FF) leaves the finish rightwards, a start-anchored one (SS, SF) leaves the start leftwards, and a link into a finish arrives from the right so it never runs the length of the bar it points at. Two tasks scheduled back to back - the everyday case - would need the arrow to hook round to reach the successor's start from the left, so it drops straight into the top of the successor instead, head pointing down; a milestone that follows its predecessor gets the same straight drop onto its apex. Only a link whose successor sits before its predecessor takes the long way round, along the boundary between the two rows.

Provide them as a flat dependencies array, or per row through dependencyField - a field on the predecessor holding either an array of GanttDependency objects, or just a list of its successors' ids (each becomes an FS link from that row):

<SvGrid {data} {columns} getRowId={(r) => r.id}
  gantt={{ startField: 'start', endField: 'end', parentField: 'parentId', dependencyField: 'next' }} />

The per-row form suits rows that come from an API with a successors or next column; the flat array suits a links table of its own. Both feed the same graph. A per-row object may leave from out - it is the row - and id out, in which case the link is named from->to.

A link that is not currently satisfied - a successor sitting too early to be legal - draws as a dashed red arrow. It is not an error: a plan mid-edit, or one imported from a tool with different rules, can have several, and the chart shows them rather than moving anything on its own.

Cyclic links are ignored rather than flagged: with a cycle there is no answer to what "late" would mean, and ignoring them is what stops an auto-reschedule from looping. A link pointing at a row the grid has filtered out simply draws nothing.

A link into a collapsed phase re-anchors on that phase's summary bar, so folding a phase never makes an arrow disappear; a link between two tasks of the same folded phase is not drawn at all. See work breakdown.

Auto-reschedule

With dependencies present and editing on, moving or resizing a task pushes its successors forward far enough to keep every link legal, preserving each one's duration. The shifts arrive together in onDependenciesChange, one entry per task that moved:

<SvGrid {data} {columns} getRowId={(r) => r.id}
  gantt={{
    startField: 'start', endField: 'end', parentField: 'parentId',
    dependencies,
    editable: true,
    onTaskMove: (e) => writeSpan(e.row, e.start, e.end),
    onTaskResize: (e) => writeSpan(e.row, e.start, e.end),
    onDependenciesChange: (moves) => {
      for (const m of moves) {
        const row = data.find((r) => r.id === m.id)
        if (row) writeSpan(row, m.start, m.end)
      }
    },
  }} />

Three rules:

Set autoReschedule: false to draw the arrows without moving anything.

With editable, every bar grows a dot at each end on hover. Drag a dot onto another bar and onDependencyAdd fires with the new link; the edge you drag from and the half of the bar you drop on pick the type - finish to start is FS, start to start SS, and so on. Right-click an arrow for Remove link, which fires onDependencyRemove with its id.

A link that would close a cycle, or one that already exists, is refused: both bars flash and no callback fires. The plan editing demo logs every one of these callbacks as they happen:

Open the live example: Plan editing (Gantt)

The view never edits the dependencies array itself. Add the link in onDependencyAdd and pass the new array back in - a $derived config is the usual way, as the demo does.