Gantt chart mode

Set one gantt prop and the grid renders its rows as a task table beside a time chart: one bar per row, placed by its start and finish, nested into a work-breakdown tree, with arrows between linked tasks. It is the same <SvGrid>, the same data and columns - only the presentation changes.

Like Kanban board mode and the scheduler, the Gantt is a pure view of the grid: it renders the grid's already filtered, sorted and searched rows and writes back only through callbacks - it never mutates your data.

Enterprise feature. The gantt prop and its config types are part of the free grid, but the renderer ships in @svgrid/enterprise. Register it once and the view lights up:

import { setLicenseKey, enableGanttView } from '@svgrid/enterprise'
setLicenseKey('YOUR-KEY')   // omit to run soft-gated with a watermark
enableGanttView()

installEnterprise(api) also calls enableGanttView() for you. Without the renderer registered, a grid with a gantt prop shows an upgrade note.

Every example below runs against this setup.

<script lang="ts">
  import { SvGrid, type GridColumns, type GanttDependency } from '@svgrid/grid'
  import { enableGanttView, type GanttProConfig } from '@svgrid/enterprise'

  enableGanttView()

  // One row type wide enough for every example on this page.
  type Task = {
    id: string
    name: string
    owner?: string
    start: string
    end?: string
    days?: number
    progress?: number
    parentId?: string | null
    milestone?: boolean
    color?: string
    blockedBy?: string[]
    bStart?: string
    bEnd?: string
  }

  // Anchored on a Monday so the weekend shading is obvious in every sample.
  const pad = (n: number) => String(n).padStart(2, '0')
  const isoDay = (d: Date) => `${d.getFullYear()}-${pad(d.getMonth() + 1)}-${pad(d.getDate())}`
  const base = new Date()
  base.setHours(0, 0, 0, 0)
  base.setDate(base.getDate() - ((base.getDay() + 6) % 7))
  const at = (dayOffset: number) => {
    const d = new Date(base)
    d.setDate(d.getDate() + dayOffset)
    return isoDay(d)
  }

  let data = $state<Task[]>([
    { id: 'p1', name: 'Discovery', parentId: null, start: at(0), owner: 'Priya' },
    { id: 't1', name: 'Interviews', parentId: 'p1', start: at(0), end: at(4), progress: 100, owner: 'Priya', bStart: at(0), bEnd: at(3) },
    { id: 't2', name: 'Synthesis', parentId: 'p1', start: at(5), end: at(11), progress: 40, owner: 'Marco', bStart: at(4), bEnd: at(9) },
    { id: 'p2', name: 'Build', parentId: null, start: at(12), owner: 'Sven' },
    { id: 't3', name: 'Implementation', parentId: 'p2', start: at(12), end: at(25), progress: 10, owner: 'Sven', bStart: at(10), bEnd: at(23) },
    { id: 'm1', name: 'Launch', parentId: null, start: at(26), milestone: true },
  ])

  const rows = data
  const tasks = data
  const dependencies: GanttDependency[] = [
    { id: 'd1', from: 't1', to: 't2' },
    { id: 'd2', from: 't2', to: 't3' },
    { id: 'd3', from: 't3', to: 'm1' },
  ]
  const holidays = [at(17)]

  const columns: GridColumns<Task> = [
    { field: 'name', header: 'Task', width: 200 },
    { field: 'owner', header: 'Owner', width: 100 },
    { field: 'start', header: 'Start', width: 110 },
    { field: 'end', header: 'Finish', width: 110 },
  ]

  // The view reports what it wants and never writes your rows, so every editing
  // example needs this. `end` is exclusive on the way back, and these rows store
  // an inclusive date-only finish, so it subtracts a day.
  function writeSpan(row: Task, start: Date, end: Date) {
    row.start = isoDay(start)
    const last = new Date(end.getTime() - 86_400_000)
    row.end = isoDay(last < start ? start : last)
  }

  // Resources for the load-strip example, with a capacity field of their own.
  const crews = [
    { id: 'Priya', title: 'Priya', cap: 2 },
    { id: 'Marco', title: 'Marco', cap: 1 },
    { id: 'Sven', title: 'Sven', cap: 1 },
  ]

  // The Enterprise config is a superset of the free grid's, so the `gantt` prop
  // accepts it - but an inline object literal is checked against the narrower
  // type. Real code writes `const cfg: GanttProConfig<any, Task> = { ... }`;
  // this one-liner is just so the Pro examples below can stay inline.
  const pro = (c: GanttProConfig<any, Task>) => c
</script>

The minimum

Point gantt.startField at the field holding each task's start. That is the only required option. With an endField too, bars get their real length. The title defaults to the first column's field.

<SvGrid {data} {columns} gantt={{ startField: 'start', endField: 'end' }} />

How dates are read

Three rules, worth knowing before you shape your data:

Instead of an end you can give a length in working days with durationField. A three-day task starting Thursday ends Tuesday, because the weekend is skipped:

<SvGrid {data} {columns}
  gantt={{ startField: 'start', durationField: 'days', nonWorkingDays: [0, 6] }} />

Work breakdown

Set parentField to the field holding each row's parent id and the flat rows nest into a tree. A row with children gets a collapse chevron and draws a summary bar rolled up from every descendant, so a phase carries no dates of its own - there is nothing to keep in sync by hand.

<SvGrid {data} {columns}
  gantt={{
    startField: 'start', endField: 'end',
    parentField: 'parentId',
    progressField: 'progress',
  }} />

A summary's percent is weighted by duration, not by task count: a two-day task at 100% beside a six-day task at 0% reads as 25% done, not 50%. Weighting by count would report progress the plan has not made. Descendants with no duration (milestones) weigh nothing, so a parent holding only milestones falls back to their plain mean.

Rows whose parent id matches no task become roots rather than vanishing, which is what keeps a filtered-out phase from hiding its tasks.

Do not also set treeData. The Gantt owns its own tree because it needs every descendant - a collapsed phase still contributes to its summary bar - whereas treeData hides collapsed children from the view before the renderer sees them. Setting both makes summaries under-report, and the grid warns about it in development.

Collapse is the Gantt's own state by default. Hoist it with collapsed and onCollapseChange to persist it or drive it from elsewhere:

<SvGrid {data} {columns}
  gantt={{
    startField: 'start', endField: 'end', parentField: 'parentId',
    collapsed: ['p1'],
    onCollapseChange: (next) => console.log('collapsed', next),
  }} />

Bars, progress and milestones

Option What it draws
progressField A 0-100 fill inside the bar, and the rollup on parents.
milestoneField A diamond instead of a bar. A zero-length task is one anyway.
colorField / color The bar's accent, per task or for all of them.
summaryBars false draws parents as ordinary bars instead of a rolled-up spine.
labelPosition 'inside' (default, falling back to the right when the bar is too narrow), 'right', or 'none'.
task A snippet for a custom bar body, in place of the label.
<SvGrid {data} {columns}
  gantt={{
    startField: 'start', endField: 'end', parentField: 'parentId',
    progressField: 'progress',
    milestoneField: 'milestone',
    colorField: 'color',
    labelPosition: 'right',
  }} />

Dependencies

Link tasks with predecessor -> successor dependencies and the chart draws an arrow between them. Four link types are supported - FS (finish-to-start, the default), SS, FF, SF - plus an optional lag in days (negative for a lead).

<SvGrid {data} {columns}
  gantt={{
    startField: 'start', endField: 'end', parentField: 'parentId',
    dependencies,
  }} />

from / to are row ids (your getRowId). Provide them as a flat dependencies array, or per row through dependencyField - an array of GanttDependency objects, or just a list of successor ids:

<SvGrid {data} {columns}
  gantt={{ startField: 'start', endField: 'end', dependencyField: 'blockedBy' }} />

A link that is not currently satisfied - a successor sitting too early to be legal - draws as a dashed red arrow. Cyclic links are ignored rather than flagged: with a cycle there is no answer to what "late" would mean, and ignoring them is what stops an auto-reschedule from looping.

A link pointing into a collapsed phase re-anchors on that phase's summary bar, so folding a phase never makes an arrow disappear. A link to a row the grid has filtered out simply draws nothing.

Editing

Set editable and the chart becomes a plan you can change: drag a bar to move it, drag either edge to resize, drag the diamond on the fill to set percent, and drag the handle at a bar's end onto another bar to draw a link.

The view never mutates your rows. It moves its own overlay so the drag is live, and reports what it wants through a callback; writing the row is yours.

<SvGrid {data} {columns}
  gantt={{
    startField: 'start', endField: 'end', parentField: 'parentId',
    progressField: 'progress',
    dependencies,
    editable: true,
    history: true,
    drawer: true,
    onTaskMove: (e) => {
      writeSpan(e.row, e.start, e.end)
      // A phase carries its children: one callback, the whole batch.
      for (const s of e.subtree ?? []) writeSpan(s.row, s.start, s.end)
    },
    onTaskResize: (e) => writeSpan(e.row, e.start, e.end),
    onProgressChange: (e) => { e.row.progress = e.progress },
    onDependenciesChange: (moves) => {
      for (const m of moves) {
        const row = data.find((r) => r.id === m.id)
        if (row) writeSpan(row, m.start, m.end)
      }
    },
  }} />

end is exclusive on the way back too. If your rows store an inclusive date-only finish, subtract a day when you write it:

function writeSpan(row: Task, start: Date, end: Date) {
  row.start = isoDay(start)
  const last = new Date(end.getTime() - 86_400_000)
  row.end = isoDay(last < start ? start : last)
}

What each gesture reports

Gesture Callback Notes
Drag a bar onTaskMove Keeps the duration. Dragging a phase moves its whole subtree and fills subtree with the batch.
Drag an edge onTaskResize edge says which one. A bar never shrinks below a day.
Drag the progress diamond onProgressChange Whole 5% steps. Leaves only; a phase shows its rollup.
Drag a bar's end handle onto another bar onDependencyAdd The edge you drag from and the half you drop on pick FS / SS / FF / SF.
Right-click an arrow onDependencyRemove
Double-click empty space onTaskAdd Creates a one-day task in that row's phase.
Drawer save onTaskCommit Start, Finish and Progress are pinned above the column fields.

A drag under three pixels counts as a click, so clicking a bar still opens the drawer rather than nudging the plan by a day.

Auto-reschedule

With dependencies present, moving or resizing a task pushes its successors forward far enough to keep every link legal, preserving each one's duration. The shifts arrive together in onDependenciesChange. Cascading only ever pushes forward - it never pulls a task earlier - and with respectWorkingTime (on by default) a cascaded start lands on a working day.

Set autoReschedule: false to draw the arrows without moving anything.

A link that would close a cycle, or one that already exists, is refused: both bars flash and no callback fires. A cycle has no legal schedule, so there is nothing the cascade could do with it.

Keyboard

Bars are focusable, so the whole plan is reachable without a mouse.

Key Does
Left / Right Move a day. With Shift, a week. With Alt, stretch the finish.
+ / - Step progress by 5.
Enter Open the drawer.
Delete onTaskDelete.
Escape Cancel the drag in progress, restoring the bar.
Ctrl/Cmd+Z, Ctrl/Cmd+Shift+Z Undo / redo, with history.

Undo re-fires the callbacks with the reversed values, cascade included, so your data follows it back rather than drifting out of step with the chart.

Working time and the axis

Non-working days are shaded, and every duration and cascade calculation skips them.

<SvGrid {data} {columns}
  gantt={{
    startField: 'start', endField: 'end',
    nonWorkingDays: [0, 6],   // Sun + Sat, the default
    holidays,
    weekStartsOn: 1,
    zoom: 'week',
  }} />

Five axis presets, each a tick unit under a coarser grouping row:

zoom Ticks Grouped by
day days (named) weeks
week (default) days months
month weeks months
quarter months quarters
year months years

The toolbar shows a zoom stepper over zoomLevels (all five by default; a single entry hides it), and Ctrl/Cmd+wheel over the chart steps it too, keeping the date under the pointer fixed. onZoomChange reports the change.

The window spans the first start to the last finish plus rangePaddingDays (7) of slack, clamped by minDate / maxDate. A dashed today line crosses the chart (todayLine: false to hide it).

The task table

The left pane lists the same rows. By default it shows every column that has a field; name and order them with tableColumns, which also accepts two built-ins that need no column definition:

<SvGrid {data} {columns}
  gantt={{
    startField: 'start', endField: 'end', parentField: 'parentId',
    progressField: 'progress',
    tableColumns: ['name', 'owner', '__duration', '__progress'],
    tableWidth: 340,
    rowHeight: 34,
  }} />

Drag the divider to resize the pane. The table and the chart share one scroll container, so their rows can never drift apart.

The pane is a compact list, not a second grid: it has no inline editing or per-column menus. Sorting and filtering happen on the grid itself, which is why the usual pattern is a Gantt / Table toggle over the same rows (demo 474 shows it) - flip the gantt prop off and the full table is back, with every column feature.

Search, filter and sort flow through

The Gantt draws the rows the grid hands it, after filtering and sorting. So the search box above the chart, any column filters, and the sort order all apply without the view knowing about them.

Sorting reorders tasks within each phase; children stay under their parent.

Gantt Pro

Five options turn the chart from a picture of the plan into a tool for questioning it. They live on GanttProConfig, the Enterprise superset of the gantt config - structurally assignable to the prop, so the free grid never needs to know about them:

import type { GanttProConfig } from '@svgrid/enterprise'

const cfg: GanttProConfig<any, Task> = { startField: 'start', /* ... */ }

The critical path

criticalPath: true runs the two passes every planner knows: a forward one giving each task its earliest start and finish, a backward one giving it its latest. Where the two agree the task has no slack - it cannot slip a day without moving the project's finish - and that chain, with the arrows along it, is ringed in red.

<SvGrid {data} {columns}
  gantt={pro({
    startField: 'start', endField: 'end', parentField: 'parentId',
    dependencies,
    criticalPath: true,
    tableColumns: ['name', '__duration', '__slack'],
    onCriticalPathChange: (keys) => console.log('critical', keys),
  })} />

Two rules worth knowing, because both are judgement calls rather than arithmetic:

The pass is a pure function, so a report or a test can call it without rendering anything:

import { criticalPath, slackDays } from '@svgrid/enterprise'

const result = criticalPath(times, dependencies)
result.critical              // Set<string> of task ids
result.finish                // the earliest the project can end
slackDays(result, 'task-7')  // whole days of room

Baselines

baselineStartField / baselineEndField draw the originally agreed dates as a ghost bar under each task. Where the plan now finishes later than the baseline did, the ghost turns red and the tooltip says by how many days.

<SvGrid {data} {columns}
  gantt={pro({
    startField: 'start', endField: 'end', parentField: 'parentId',
    baselineStartField: 'bStart', baselineEndField: 'bEnd',
    tooltip: true,
  })} />

Constraints

constraintField pins a task's dates in the classic planning vocabulary, with the date itself in constraintDateField:

Constraint Means
ASAP (default) Schedule as early as the links allow.
MSO / MFO Must start / finish on the date.
SNET / SNLT Start no earlier / no later than.
FNET / FNLT Finish no earlier / no later than.

A constrained bar carries a small glyph, and one whose own dates already break its rule is flagged. More usefully, the cascade respects the ceiling: pushing a chain into a task that must finish by a contract date stops at the date and leaves the link drawn as unsatisfied, rather than overrunning it silently. A constraint and a dependency that disagree have no schedule satisfying both, so showing the conflict beats breaking one of them behind your back.

Resource load

resourceField names the field holding who is on each task; resourceHistogram sums them into a strip under the chart - one row per resource, one bar per axis column, counting the tasks that touch it, with anything past capacity in red.

<SvGrid {data} {columns}
  gantt={pro({
    startField: 'start', endField: 'end', parentField: 'parentId',
    resourceField: 'owner',
    resources: crews,
    resourceHistogram: { capacityField: 'cap', height: 80 },
  })} />

A cell's number is how many of that resource's tasks overlap the column, not an average and not person-hours. On a day or week axis that is exactly concurrency; on a coarser one it counts everything touching the column, which reads high rather than low. Only leaves are counted - a phase is its children, so counting it too would book its owner twice for the same work.

Omit resources and the rows come from the data, in the order the tasks first name them, each with a capacity of one. resourceField on its own (no histogram) still puts the resource in the tooltip.

A folded axis

collapseWeekends takes the whole non-working days out of the timeline and leaves a narrow hatched marker where each run was, so a quarter fits in the width a month used to take. Working days keep their real size - nothing is squashed - and a task that does run over a folded weekend still draws across it.

<SvGrid {data} {columns}
  gantt={pro({
    startField: 'start', endField: 'end', parentField: 'parentId',
    zoom: 'week', collapseWeekends: true, collapsedGapPx: 10,
  })} />

collapsedGapPx: 0 removes the folded days outright: Friday's finish and Monday's start land on the same pixel. Only the day-granular presets (day, week) have weekend columns to fold; at month and coarser a tick is never wholly non-working, so the option is ignored rather than shrinking a week by part of itself.

Pro config reference

Option Purpose
criticalPath / onCriticalPathChange Ring the chain with no slack, and report its task ids.
baselineStartField / baselineEndField The agreed dates, drawn as a ghost bar under each task.
constraintField / constraintDateField Pin a task's dates; the cascade stops at the constraint.
resourceField / resources Who is on each task, and the ordered resource list.
resourceHistogram The load strip: true, or { capacityField, height }.
collapseWeekends / collapsedGapPx Fold non-working days out of the axis, and the marker's width.

Config reference

Option Purpose
startField (required) Field holding each task's start.
endField Field holding the finish. A date-only string is inclusive of its day.
durationField Length in WORKING days, used when endField is absent.
titleField The task name. Defaults to the first column's field.
progressField Percent complete (0-100); drives the fill and the rollup.
parentField Parent task id - nests the rows into a work-breakdown tree.
milestoneField Boolean marking a milestone. A zero-length task is one anyway.
colorField / color Per-task accent, or one for every bar.
dependencies / dependencyField Links ({ id, from, to, type?, lag? }), as a flat list or per row. lag is in days.
autoReschedule / respectWorkingTime Cascade successors forward on an edit, landing on working days.
onDependenciesChange / onDependencyAdd / onDependencyRemove The link callbacks.
zoom / zoomLevels / onZoomChange The axis preset, the stepper's presets, and the change callback.
weekStartsOn First day of the week, 0-6 (default 0).
nonWorkingDays / holidays / showNonWorking Which days are off, and whether to shade them.
todayLine The dashed today line. On by default.
minDate / maxDate / rangePaddingDays The axis window and its slack.
tableColumns / tableWidth The task pane's columns (incl. __duration, __progress) and width.
rowHeight Height of one task row (default 32).
summaryBars / labelPosition Parent bar style, and where a bar's label sits.
collapsed / onCollapseChange Controlled work-breakdown collapse.
editable / history Drag to move, resize, set progress and draw links; undo / redo.
onTaskMove / onTaskResize / onProgressChange Fired with the new values; write them to your rows.
onTaskAdd / onTaskDelete Create on a double-click of empty space; delete from the menu.
task / tooltip / tooltipDelay A custom bar body, and the hover tooltip.
drawer / onTaskCommit The built-in detail drawer and its save callback.
taskMenu Right-click menu items for a bar.
searchable / searchPlaceholder The toolbar search box.

More examples

Plan editing

Every gesture with a log panel listing the callbacks it fires: drag, resize, the progress grip, drawing links, auto-reschedule over a holiday, and undo.

Critical path & baselines

A fit-out schedule with the planning layer on: the chain with no slack ringed in red, a Slack column for everything else, baseline ghosts that redden where the plan has drifted, and two pinned tasks where a cascade stops at the constraint.

Resource load & a folded axis

A field-service quarter with a load strip under the chart, per-resource capacity, and the weekends folded out of the timeline.