Critical path & baselines
A fit-out schedule with the planning layer on: the chain with no slack ringed in red with its arrows, a Slack column for everything else, baseline ghosts that redden where the plan has drifted, and two pinned tasks where a cascade stops at the constraint instead of running past it. (requires @svgrid/enterprise)
A live, editable Svelte 5 data grid example from the SvGrid gallery (Gantt). See the SvGrid documentation for the full API.
About this example
Project planning on the Svelte 5 data grid's Gantt view: the critical path, baselines and scheduling constraints. The chain of tasks with no slack is ringed in red along with the arrows between them, and a Slack column says how many days of room each of the others has. Baseline dates draw as a ghost bar under each task, turning red where the plan has drifted late. Two tasks carry constraints, so a cascade stops at a contractual finish date rather than running past it and the blocked link stays drawn as unsatisfied.
A fit-out schedule with the planning layer on:
- **Critical path.** The chain of tasks with no slack, ringed in red along with the arrows between them. Slip any of these and the handover date moves; the others have room, and the Slack column says how much.
- **Baselines.** The originally agreed dates draw as a ghost bar under each task. Where the plan has drifted, the ghost turns red and the tooltip says by how many days.
- **Constraints.** Two tasks are pinned: the inspection cannot start before its booked date (
SNET) and handover must finish by its contract date (FNLT). Drag the chain right and the cascade stops AT the ceiling rather than running past it, leaving the link drawn as unsatisfied - which is the honest answer when a constraint and a dependency disagree.
Drag a bar and watch the path recompute: shortening a critical task hands the title to whichever chain is longest next.
Imports, features and API used
Imports: @svgrid/grid, @svgrid/enterprise
Columns: name (Task), trade (Trade), start (Start), end (Finish)
Frequently asked questions
What makes a task critical?
It has no slack: a forward pass gives every task its earliest start and a backward pass its latest, and where those are the same the task cannot slip a day without moving the project finish. A task in no dependency at all is never marked critical, because it is not on any path.
What does the ghost bar under a task mean?
The baseline, the dates originally agreed. It turns red when the current plan finishes later than the baseline did, and the tooltip says by how many days.
What happens when a constraint and a dependency disagree?
The cascade stops at the constraint rather than overrunning it, and the link is left drawn as unsatisfied. There is no schedule that satisfies both, so showing the conflict is more useful than silently breaking one of them.
Related documentation
Source code (476-gantt-critical-path.svelte)
<script lang="ts">
/**
* 476. Critical path & baselines (Enterprise Gantt Pro)
* ------------------------------------------------------
* A fit-out schedule with the planning layer on:
*
* - **Critical path.** The chain of tasks with no slack, ringed in red
* along with the arrows between them. Slip any of these and the
* handover date moves; the others have room, and the Slack column
* says how much.
* - **Baselines.** The originally agreed dates draw as a ghost bar under
* each task. Where the plan has drifted, the ghost turns red and the
* tooltip says by how many days.
* - **Constraints.** Two tasks are pinned: the inspection cannot start
* before its booked date (`SNET`) and handover must finish by its
* contract date (`FNLT`). Drag the chain right and the cascade stops
* AT the ceiling rather than running past it, leaving the link drawn
* as unsatisfied - which is the honest answer when a constraint and a
* dependency disagree.
*
* Drag a bar and watch the path recompute: shortening a critical task
* hands the title to whichever chain is longest next.
*/
import { SvGrid, type ColumnDef, type GanttDependency } from '@svgrid/grid'
import { enableGanttView, type GanttProConfig } from '@svgrid/enterprise'
enableGanttView()
type Task = {
id: string
name: string
trade: string
start: string
end?: string
progress: number
parentId: string | null
milestone?: boolean
color?: string
/** The originally agreed dates. */
bStart?: string
bEnd?: string
con?: 'SNET' | 'FNLT'
conDate?: string
}
const TRADE = {
strip: '#7c3aed',
build: '#2563eb',
fit: '#0891b2',
sign: '#16a34a',
} as const
const pad = (n: number) => String(n).padStart(2, '0')
const iso = (d: Date) => `${d.getFullYear()}-${pad(d.getMonth() + 1)}-${pad(d.getDate())}`
const base = new Date()
base.setHours(0, 0, 0, 0)
base.setDate(base.getDate() - ((base.getDay() + 6) % 7) - 7)
const at = (d: number) => {
const x = new Date(base)
x.setDate(x.getDate() + d)
return iso(x)
}
/**
* The inclusive finish of a task that starts `from` days from the anchor
* (a Monday) and runs `days` WORKING days: every task starts on a weekday
* and ends on one, the way a real plan is typed in.
*/
const wd = (from: number, days: number) => {
let d = from
for (let left = days; left > 1; left--) {
d += d % 7 === 4 ? 3 : 1 // Friday -> Monday
}
return at(d)
}
// The long chain runs back to back in working time - strip, structure,
// services, commissioning, handover, each starting the working day after
// the last one ends - so none of it has a day to give: that is what makes
// it critical. Joinery and signage branch off with real room.
let rows = $state<Task[]>([
{ id: 'p1', name: 'Shell', trade: 'strip', start: at(0), progress: 0, parentId: null, color: TRADE.strip },
{ id: 't1', name: 'Strip out', trade: 'strip', start: at(0), end: wd(0, 5), progress: 100, parentId: 'p1', color: TRADE.strip, bStart: at(0), bEnd: wd(0, 4) },
{ id: 't2', name: 'Structural works', trade: 'build', start: at(7), end: wd(7, 10), progress: 70, parentId: 'p1', color: TRADE.build, bStart: at(7), bEnd: wd(7, 7) },
{ id: 'p2', name: 'Fit-out', trade: 'fit', start: at(21), progress: 0, parentId: null, color: TRADE.fit },
{ id: 't3', name: 'Services rough-in', trade: 'fit', start: at(21), end: wd(21, 10), progress: 30, parentId: 'p2', color: TRADE.fit, bStart: at(16), bEnd: wd(16, 10) },
// The short branch: it feeds commissioning too, but finishes with days
// to spare, so it is not what the handover date turns on.
{ id: 't4', name: 'Joinery', trade: 'fit', start: at(21), end: wd(21, 5), progress: 20, parentId: 'p2', color: TRADE.fit, bStart: at(21), bEnd: wd(21, 5) },
{ id: 't5', name: 'Signage & branding', trade: 'sign', start: at(28), end: wd(28, 3), progress: 0, parentId: 'p2', color: TRADE.sign, bStart: at(28), bEnd: wd(28, 3) },
{ id: 'p3', name: 'Handover', trade: 'sign', start: at(35), progress: 0, parentId: null, color: TRADE.sign },
// Pinned: the inspector is booked and cannot come earlier.
{ id: 't6', name: 'Commissioning', trade: 'fit', start: at(35), end: wd(35, 5), progress: 0, parentId: 'p3', color: TRADE.fit, bStart: at(30), bEnd: wd(30, 5), con: 'SNET', conDate: at(35) },
// Pinned: the lease says the keys change hands by this date.
{ id: 't7', name: 'Snagging & handover', trade: 'sign', start: at(42), end: wd(42, 5), progress: 0, parentId: 'p3', color: TRADE.sign, bStart: at(37), bEnd: wd(37, 5), con: 'FNLT', conDate: at(49) },
{ id: 'm1', name: 'Keys handed over', trade: 'sign', start: at(49), progress: 0, parentId: null, milestone: true, color: '#f59e0b' },
])
const dependencies: GanttDependency[] = [
{ id: 'd1', from: 't1', to: 't2' },
{ id: 'd2', from: 't2', to: 't3' },
{ id: 'd3', from: 't2', to: 't4' },
{ id: 'd4', from: 't3', to: 't6' },
{ id: 'd5', from: 't4', to: 't5' },
{ id: 'd6', from: 't5', to: 't6' },
{ id: 'd7', from: 't6', to: 't7' },
{ id: 'd8', from: 't7', to: 'm1' },
]
const columns: ColumnDef<any, Task>[] = [
{ field: 'name', header: 'Task', width: 190 },
{ field: 'trade', header: 'Trade', width: 90 },
{ field: 'start', header: 'Start', width: 110 },
{ field: 'end', header: 'Finish', width: 110 },
]
let criticalKeys = $state<string[]>([])
const nameOf = (id: string) => rows.find((r) => r.id === id)?.name ?? id
const criticalLeaves = $derived(
criticalKeys.filter((k) => rows.find((r) => r.id === k)?.parentId != null),
)
const iso2 = (d: Date) => iso(d)
function writeSpan(row: Task, start: Date, end: Date) {
row.start = iso2(start)
const last = new Date(end.getTime() - 86400000)
row.end = iso2(last < start ? start : last)
}
const byId = (id: string) => rows.find((r) => r.id === id)
const cfg: GanttProConfig<any, Task> = {
startField: 'start',
endField: 'end',
titleField: 'name',
progressField: 'progress',
parentField: 'parentId',
milestoneField: 'milestone',
colorField: 'color',
tableColumns: ['name', 'trade', '__duration', '__slack'],
dependencies,
zoom: 'month',
weekStartsOn: 1,
// Room on the right for the last bars' labels.
rangePaddingDays: 14,
// --- the planning layer -------------------------------------------------
criticalPath: true,
onCriticalPathChange: (keys) => (criticalKeys = keys),
baselineStartField: 'bStart',
baselineEndField: 'bEnd',
constraintField: 'con',
constraintDateField: 'conDate',
editable: true,
tooltip: true,
onTaskMove: (e) => {
writeSpan(e.row, e.start, e.end)
for (const s of e.subtree ?? []) writeSpan(s.row, s.start, s.end)
},
onTaskResize: (e) => writeSpan(e.row, e.start, e.end),
onDependenciesChange: (moves) => {
for (const m of moves) {
const r = byId(m.id)
if (r) writeSpan(r, m.start, m.end)
}
},
}
// The same rows as a plain table: the Gantt is one view of the grid.
let view = $state<'gantt' | 'table'>('gantt')
</script>
<section class="cp">
<header class="cp-head">
<div class="cp-title">
<strong>Unit 4 fit-out</strong>
<span class="cp-sub">
Red rings mark the chain with no slack - slip any of it and the handover moves.
Grey ghosts are the agreed baseline, red ones mean the plan has drifted late,
and the pins are the two dates the contract holds tasks to.
</span>
</div>
<div class="cp-legend">
<span class="cp-key"><span class="cp-swatch cp-swatch-crit"></span>Critical</span>
<span class="cp-key"><span class="cp-swatch cp-swatch-base"></span>Baseline</span>
<span class="cp-key"><span class="cp-swatch cp-swatch-late"></span>Behind it</span>
<span class="cp-key"><span class="cp-pin"></span>Pinned date</span>
</div>
<div class="cp-seg" role="tablist" aria-label="View">
<button class="cp-seg-btn" role="tab" aria-selected={view === 'gantt'} class:cp-on={view === 'gantt'} onclick={() => (view = 'gantt')}>Gantt</button>
<button class="cp-seg-btn" role="tab" aria-selected={view === 'table'} class:cp-on={view === 'table'} onclick={() => (view = 'table')}>Table</button>
</div>
</header>
{#if criticalLeaves.length}
<p class="cp-path">
<strong>Critical path:</strong>
{criticalLeaves.map(nameOf).join(' → ')}
</p>
{/if}
<div class="cp-body">
{#if view === 'gantt'}
<SvGrid
columnResize
data={rows}
columns={columns}
getRowId={(r) => r.id}
containerHeight="100%"
gantt={cfg}
/>
{:else}
<SvGrid columnResize data={rows} columns={columns} getRowId={(r) => r.id} containerHeight="100%" sortable fitColumns />
{/if}
</div>
</section>
<style>
.cp {
display: flex;
flex: 1 1 auto;
flex-direction: column;
min-height: 0;
border: 1px solid var(--sg-border, #e5e7eb);
border-radius: 12px;
overflow: hidden;
background: var(--sg-bg, #fff);
}
.cp-head {
display: flex;
align-items: flex-start;
justify-content: space-between;
gap: 14px;
padding: 10px 14px;
border-bottom: 1px solid var(--sg-border, #e5e7eb);
}
.cp-title { display: flex; flex-direction: column; gap: 2px; min-width: 0; }
.cp-sub { font-size: 0.78rem; color: var(--sg-muted, #6b7280); }
.cp-legend { display: flex; flex: none; gap: 12px; padding-top: 3px; margin-left: auto; }
.cp-seg { display: inline-flex; flex: none; border: 1px solid var(--sg-border, #e5e7eb); border-radius: 8px; overflow: hidden; }
.cp-seg-btn { padding: 5px 12px; border: 0; background: transparent; color: inherit; font: inherit; font-size: 0.8rem; cursor: pointer; }
.cp-seg-btn:hover { background: color-mix(in srgb, var(--sg-fg, #1f2937) 6%, transparent); }
.cp-on { background: var(--sg-accent, #4f46e5); color: #fff; }
.cp-on:hover { background: var(--sg-accent, #4f46e5); }
.cp-key { display: inline-flex; align-items: center; gap: 5px; font-size: 0.74rem; color: var(--sg-muted, #6b7280); }
.cp-swatch { width: 12px; height: 8px; border-radius: 2px; flex: none; }
.cp-swatch-crit { background: transparent; box-shadow: 0 0 0 2px #dc2626; }
.cp-swatch-base { height: 5px; background: color-mix(in srgb, var(--sg-fg, #1f2937) 28%, transparent); }
.cp-swatch-late { height: 5px; background: color-mix(in srgb, #dc2626 45%, transparent); }
.cp-pin {
width: 0;
height: 10px;
border-left: 1.5px dashed color-mix(in srgb, var(--sg-fg, #1f2937) 60%, transparent);
position: relative;
margin: 0 5px;
}
.cp-pin::before {
content: '';
position: absolute;
top: -1px;
left: -5.5px;
border: 5px solid transparent;
border-top: 6px solid color-mix(in srgb, var(--sg-fg, #1f2937) 60%, transparent);
border-bottom: 0;
}
.cp-path {
margin: 0;
padding: 7px 14px;
font-size: 0.78rem;
color: var(--sg-fg, #374151);
background: color-mix(in srgb, #dc2626 7%, transparent);
border-bottom: 1px solid var(--sg-border, #e5e7eb);
}
.cp-body { flex: 1 1 auto; min-height: 0; padding: 8px; }
@media (max-width: 767px) {
.cp { min-width: 860px; flex-shrink: 0; }
}
</style>More Gantt examples
- Project plan - A 14-week release as a Gantt: phases nest their tasks and draw a rolled-up summary bar, finish-to-start links draw as arrows, and a violated one turns red. Collapse a phase and its summary keeps the span. Toggle to the Table - same grid rows, just a view. The renderer ships in @svgrid/enterprise.
- Plan editing - The same plan with editing on: drag a bar or its edges, drag the diamond to set percent, drag a dot onto another bar to draw a link. A phase moves its whole subtree in one callback, successors slide forward over weekends, a cycle is refused, and Ctrl+Z replays it backwards. A log panel lists every write-back the view asks for.
- Resource load & folded axis - A field-service quarter with a load strip under the chart: one row per crew, one bar per column, red where a crew is booked past its capacity - the specialist is one person with two sign-offs in the same week. Capacity is per resource, so a two-van crew takes two jobs at once. Fold the weekends out and the quarter fits in the width a month used to take.
- One plan, four views: Grid, Gantt, Scheduler, Kanban - One <SvGrid>, one array, four renderers behind a switch: the plain table with inline editing, the Gantt with phases and links, a resource timeline with a lane per owner, and a Kanban of status lanes. Every view writes back through a callback to the same rows - change a status in the grid and the card moves lane, drag a bar in the Gantt and the timeline follows - and a line under the switcher names the last write.
- Product roadmap - a year in quarters - The Gantt as a roadmap: three teams, their initiatives across four quarters, and the releases that cut across them as milestones. A `task` snippet draws the owner and a status chip inside each bar, colour is by status, a custom tooltip carries the effort and a summary, the header chips filter by status, and a month / quarter / year zoom ladder drills in with Ctrl+wheel.